TIC (Total Investment Cost, 총투자비) 산출

AACE, Classification of capital cost estimates

TIC 산출 관련한 class

AACE, Cost Engineering Techniques and Their Applicability for Cost Estimation of Organic Rankine Cycle Systems
((https://www.mdpi.com/1996-1073/9/7/485))
((AACE® International Professional Guidance Document No. 01 GUIDE TO COST ESTIMATE CLASSIFICATION SYSTEMS -- https://library.aacei.org//pgd01/pgd01.shtml))

Class Type of Estimate Description Accuracy Range
5 Order-of-magnitude estimate(also Ratio/Feasibility) Based on limited information. Concept screening. Low: -20%-50%, High: +30%+100%
4 Study estimate (also Major Equipment/Factored) List of major equipment. Project screening, feasibility assessment, concept evaluation, and preliminary budget approval. Low: -15%-30%, High: +20%+50%
3 Preliminary design estimate (also Scope) More detailed sizing of equipment. Budget authorization, appropriation, and/or funding. Low: -10%-20%, High: +10%+30%
2 Definitive estimate (also Project Control) Preliminary specification of all the equipment, utilities, instrumentation, electrical and off-sites. Control or Bid/Tender. Low: -5%-15%, High: +5%+20%
1 Detailed estimate (also Firm/Contractor's) Complete engineering of process and related off-sites and utilities required. Check Estimate or Bid/Tender. Low: -3%-10%, High: +3%+15%

Class 5 (Concept Screening) 수준의 TIC 추정

Item   2019 2020 2021 2022 2023.1-9
CE index   607.5 596.2 708.8 816.0 800.6
Capacity 200 kTA 100        
250 kTA 114       150
  • capacity 증가 관련해서는 six-tenth rule(^0.6에 비례한다)을 적용
  • 물가상승률 등은 CE index를 활용하여 증가 반영 -- [[https://toweringskills.com/financial-analysis/cost-indices/ | Bureau of Labor Statistics(BLS), Producer Prices Indices(PPI), .. Chemical Engineering Plant Cost Index(CEPCI)]]
  • 위의 예에서 2019년 capacity 200 kTA 공장 투자비를 100으로 가정한 경우, 2023년 250 kTA 공장의 투자비를 약 150로 추정

이후 location factor를 적용하여 최종 투자비를 추정합니다.

 

 

cost index와 scaling factor를 사용한 추정

주요 index

  • Marshall and Swift Installation-equipment indexes, 1926=100
  • Nelson-Farrar refinery construction index, 1946=100
  • Chemical Engineering plant cost index, 1957-1959=100

scaling factor

  • the six-tenth(6/10th) factor rule

[[https://gyansanchay.csjmu.ac.in/wp-content/uploads/2023/03/Chapter-5-Cost-Estimation-Part-2.pdf | Analysis of Cost Estimation]]

 

Class 4 (Major Equipment / Factored) 수준의 TIC 추정

Major Equipment List가 있고, 각 item의 대략적인 투자비를 in-house로 구할 수 있는 경우, 전체 프로젝트의 TIC는 아래와 같이 구할 수 있습니다.

 

1. Equipment Cost 산출:

Item KRW JPY USE EUR USD
converted
Exchange Rate 1300 100 1 0.9 1
Equipment List          
- Agitator          
- Compressor          
- Column          
- Drum          
- Heat Exchanger          
- Pump          
- Tank          
Sub-Total (mm$)     100   100

 

 

2. ISBL 투자비 산출:

위의 Equipment 투자비(여기서는 $100mm을 가정함)를 이용해서 ISBL 전체의 투자비를 추정합니다. 과거 프로젝트들의 실적을 참고하여 Equipment Cost와 타 비용간의 %를 이용해서 추정합니다.

Item Engineering Procurement-Eq. P-Bulk Construction Total
ISBL-Sum
(mm$)
20 100 50 80 250
  8% 40% 20% 32% 100%

 

3. OSBL 투자비 산출: 

한편, OSBL은 각 공장의 상황에 따라 많이 바뀌게 되므로 아래과 같이 항목별로 투자비를 추정합니다.

Item Engineering Procuement-Eq P-Bulk Construction Total
Storage tank          
Warehouse          
Cooling Tower          
Inter-connection          
Raw Water Treatment          
Waste Water Treatment          
OSBL-Sum
(mm$)
         

 

4. 기타 Owner cost:

위에서 구한 ISBL, OSBL 관련 EPC (General contractor) 비용 이외에 owner cost를 추정합니다.

구분    
License    
건설관리    
조립보험    
건설이자    
시운전    
취득세 등    
Owner-cost Sub-total    

 

5. 총 TIC:

총 TIC는 아래와 같습니다.

구분    
Owner cost    
EPC    
Total Investment Cost    

 

 

class 2 수준의 TIC 추정

'신규사업' 카테고리의 다른 글

[FS 기초#1] Boundary  (0) 2025.10.26
[FS 기초#2] 원부재료 가격  (0) 2025.10.26
[FS 기초#3] Man-power  (0) 2025.10.26
[FS 기초#5] 차입금이 있는 경우  (0) 2025.10.26
[FS 기초#6] Sample FS Model  (0) 2025.10.26

+ Recent posts